Main grid

Main grid

A virtual transmission line runs through the landscape

Constructing a transmission line is a long process, which first sees the light of day on a map, many years before becoming a feature of the landscape. Nowadays, future transmission line rights-of-way can be presented to landowners and partners with the help of 3D modelling.

Main grid

What does the expropriation procedure involve?

Expropriation is a normal means of executing a linear construction project. The procedure begins when the project commences and an expropriation permit application is submitted, and it ends when compensation is assessed and paid following construction work. Landowners have the opportunity to give their views on the transmission line route during the planning phase and the expropriation permit application phase.

Main grid

Good decentralisation in the control centre

Control Centre Manager Maarit Uusitalo is responsible for managing the power balance on the main grid and the power system from the office in Käpylä. Uusitalo, who has worked for Fingrid for a long period in several positions, took on the role of control centre manager in March this year.

Main grid

Updated transmission line brochures for landowners

Fingrid’s transmission line brochures for landowners have been updated. There were previously four brochures: two about the construction phase and two for the period after construction. As a result of the update, there are now two brochures.

Main grid

Main grid, where are you going?

The design of the main grid includes making preparations for a climate-neutral society in which the importance of electricity is constantly increasing. Over the coming decades, the emissions produced by generating electricity must be lowered, and electricity consumers must be offered the best opportunities to obtain clean electricity.

Main grid

Long lines from north to south

Fingrid is currently building transmission lines on the main grid on dozens of sites. Construction work on the main grid runs to EUR 100 million annually. The company is having a record year in terms of the number of substation modernisations and refurbishments.

Main grid

Imatra 1929 and 2020

The Imatra hydroelectric power plant began operating in 1929, along with the Imatra substation, which was the first substation on Finland’s main grid. The first transmission line on the main grid went from Imatra to Vyborg and onwards to Helsinki and Turku via Hikiä. In 2020, Fingrid commissioned a new substation in Imatra and began modernising the Imatra–Huutokoski transmission line.

Main grid

The Forest Line will ensure that Finland remains a single pricing area

The Forest Line, which runs from Muhos near Oulu to Petäjävesi in Central Finland, has been under construction since the autumn of 2019. The line will be completed in 2022, and it will be particularly significant in ensuring that Finland remains a single pricing area.

You've reached the end of this archive.